Calculate shoreline and slope stone by armor-layer depth, rather than the shallow depth used for landscaping rock.

Enter your project dimensions

ft
Enter a length greater than 0
ft
Enter a width greater than 0
ft
Enter a diameter greater than 0
in
Enter a depth between 0.25 and 24 inches
Add 5% extra for compaction & spillage

Riprap installed at 12 inches or more covers far less area than landscape stone: one ton covers about 17 square feet. This calculator estimates material by layer depth, using 3,100 lb per cubic yard for rip rap commonly sized 4 to 12 inches and above.

How to measure an armored bank

  1. Take the measurement along the sloped bank face, then multiply it by the shoreline or channel length. Do not measure across level ground.
  2. For effective erosion protection, use a 12 inches minimum layer. Set thickness at 1.5 to 2 times the largest rock dimension.
  3. Find cubic yards by dividing cubic feet by 27, then use x 1.55 to calculate tons.
Tons = (Slope-face area sq ft × Layer thickness in ÷ 12) ÷ 27 × 1.55

Tons of coverage

Layer thickness1 ton coversTons per 100 sq ft
12 inches≈ 17 sq ft5.7
18 inches≈ 12 sq ft8.6
24 inches≈ 9 sq ft11.5

Steps for stable stone placement

  • Install non-woven geotextile beneath the rock, or start with 3-4 inches of #4 stone. Bare soil can wash away below riprap, particularly where wet clay loses its shape, leaving the rock to settle after a season.
  • Set the toe before placing the rest of the stone. Place the lowest row under the waterline or anticipated scour depth, since erosion can undermine riprap from below.
  • Before placing stone, cut the bank to a 2:1 slope or gentler. A face that is steeper needs engineering, not added rock.
  • Use equipment or hand placement for the exposed top course, arranging stones so they lock together rather than sit where they land.
  • For culvert outlets, carry the apron 4-6 pipe diameters beyond the outlet downstream. This is the area where flow begins to scour the ground.

Example: 50 feet of pond bank

For a 6-foot bank face running 50 feet along the water, the area is 300 square feet. Using an 18-inch layer, calculate 300 x 1.5 = 450 cubic feet = 16.7 cubic yards, or about 26 tons of riprap. Plan for 27 with a small extra amount. Include geotextile, or use about 4 tons of #4 stone as a rock bed. Check the truck path before placing an order, since the final 20 feet near a pond can be soft enough to trap a loaded truck. Moving stone twice doubles the handling.

Following the first major storm

After the water recedes, walk along the bank and inspect the toe for rock that has moved, newly exposed soil between stones, or visible fabric. Put shifted stone back in place, use reserve material to cover thin areas, and look over the outfall apron for erosion. Ten minutes spent checking it a few times each year is generally all the upkeep needed. Riprap is intended to protect the bank with the stone doing the work.

Stone sizes at a glance

Select riprap size based on water force. Four to eight inch stone works for slow streams, pond banks and downspout outfalls. Use eight to twelve for faster channels and lake shorelines exposed to boat wake. Highways, spillways and other engineered work have specified stone classes and depths, so follow the project drawing instead of this guide. When between sizes, choose the larger rock and use a thicker layer; added weight provides more tolerance.

Riprap quantities, sizing and placement

How can I estimate the rip rap needed?
Multiply slope-face area by the layer depth in feet, then multiply by 1.55 and divide by 27. For a 10 x 10 trial section with 12 inches of stone, the result is 37 cubic feet, or about 2.1 tons.
What area will 1 ton of riprap cover?
Expect roughly 17 square feet of coverage at a 12-inch depth, or 12 square feet at 18 inches. For planning costs, allow 5.5 to 6 tons for each 100 square feet at the usual depth.
What does 1 ton of rip rap resemble?
A ton makes a pile near two-thirds cubic yard, about the volume of a washing machine. At the 6-8 inch size, that is 25-35 stones. It can look like a small pile until spread at the correct depth over a 4 x 4 section of bank.
What is the cost for 1 ton of rip rap?
Riprap costs more than construction stone and is priced by size class. Current pricing appears on our RipRap product page, with free delivery. Fabric and bedding stone increase the total by a fraction and are economical components to install correctly.
What layer depth should rip rap have?
Set the layer from twice the largest stone dimension down to one and a half times that dimension, with a 12 inches minimum. For typical 4-12 inch residential material, plan on 12-18 inches. Use 24 for larger rock or moving water.
Is hand placement possible for rip rap?
Yes, for material up to about 6-8 inch stone, using gloves and a strong back. A ton involves 25-35 lifts. Larger pieces call for machinery. In an hour, a skid steer can set what a crew might hand-place in a day.